Skip to main content
All CollectionsProjects
Creating Change Orders and Generating a Change Order Document
Creating Change Orders and Generating a Change Order Document
Ian Sharp avatar
Written by Ian Sharp
Updated this week

This guide explains how to create a change order for a project, associating it with contracts, and adding relevant details such as vendor name, order number, and order title. It also covers how to add a Schedule of Values (SOV), input the value of the change order, and generate and upload documents.

Start by navigating to the project's budget.

Step 1: Go to the Change Orders section.

Image

Here, view existing change orders or add a new one.

Step 2: Click on Add New Change Order.

Image

The system automatically selects the project.

Step 3: Select the associated contract.

Image

Image

Step 4: Input the vendor name. In this example, select Concrete Works.

Image

Image

Step 5: Enter the order number, for instance, CO-009.

Image

Image

Step 6: Add the order title, such as Additional Concrete Flooring.

Image

Step 7: Input the order date and the approved date.

Image

Image

Step 8: Change the status based on whether the order is new or approved. Additional options are available.

Image

Image

Step 9: Add any additional notes if needed, then click Submit.

Image

The data populates accordingly.

Step 10: Add a SOV to the order. This can be searched and added.

Image

Image

Image

Step 11: Input the value of the change order, for example, $10,000, and save it.

Image

Image

The SOV now appears in the scope.

Step 12: Generate the file. The file is automatically generated based on default documentation.

Image

Step 13: If needed, upload a new document. This could be a document exported from another solution, such as Procore.

Image

Step 14: Click to add the document, then click Upload.

Image

Image

That concludes the guide on creating a change order for a project. Reach out with any questions.

Did this answer your question?